Your have j ust taken control of a project in the middle of execution and need to learn who has approval authority for revisions

admin2014-11-05  27

问题  Your have j ust taken control of a project in the middle of execution and need to learn who has approval authority for revisions in scope.(4) document provides this information.

选项 A、Resource assignment matrix
B、Change control plan
C、Project charter
D、Client organization chart

答案B