The(70)provides the project manager with the authority to apply organizational resources to project activities.

admin2008-04-01  43

问题 The(70)provides the project manager with the authority to apply organizational resources to project activities.

选项 A、project management plan
B、contract
C、project human resource plan
D、project charter

答案D

解析 项目章程为项目经理使用组织资源进行项目活动提供了授权。
转载请注明原文地址:https://kaotiyun.com/show/DBGZ777K
0

相关试题推荐
随机试题
最新回复(0)