(69) is the budgeted amount for the work actually completed on the schedule activity or WB S component during a given time perio

admin2014-11-05  33

问题 (69) is the budgeted amount for the work actually completed on the schedule activity or WB S component during a given time period.

选项 A、Planned value
B、Earned value
C、Actual cost
D、Cost variance

答案B

解析
转载请注明原文地址:https://kaotiyun.com/show/DwGZ777K
0

随机试题
最新回复(0)