首页
外语
计算机
考研
公务员
职业资格
财经
工程
司法
医学
专升本
自考
实用职业技能
登录
外语
Complete the summary below. Use NO MORE THAN THREE WORDS for each answer. PROJECT MANAGENT Last week’s definition of pro
Complete the summary below. Use NO MORE THAN THREE WORDS for each answer. PROJECT MANAGENT Last week’s definition of pro
admin
2011-02-08
49
问题
Complete the summary below.
Use NO MORE THAN THREE WORDS for each answer.
PROJECT MANAGENT
Last week’s definition of project management:
Project Management has
a clear【31】
goals, budget and【32】
A project can be divided into【33】
The subject of today’s lecture【34】
LECTURER:
I’d like to begin today with a quick review of last week’s lecture. We saw the definition of project management as something which has a clear beginning and a clear completion date with goals, a budget and a schedule. We saw its presence in the private and public sectors in many different industries. You’ll also remember that we outlined the life cycle as it were, of a project and looked at the first of a four-stage cycle-establishing the limits of the project.
Today, we’re going to talk broadly about the second stage of project management-developing a plan for the project. Next week we’ll focus on the implementation of the project and then, the final stage-its evaluation.
Let’s get started on today’s topic, though-planning the project. The success of a project will depend on the skills and care which you put in at this initial planning stage. Planning is not only necessary in terms of budget or cost, it’s also crucial that you consider the time-frame of a project and the standards which you’ll be expected to provide. These three elements are, of course, integrated. Project-planning is best conducted as a team - you might have to take responsibility for handing over the final plan but without a team behind you, you’ll find it almost impossible to plan effectively.
We’ll discuss budgetary planning firstly because that is, of course, what you are most likely to be evaluated on by your own manager. Before drawing up a budget, you’ll need to understand the time-frame involved to carry out the work and the standard of delivery at which the labour and materials are to be supplied. Now, this is arguably the most difficult to plan for. You’ll never plan completely accurately for a project in terms of money but you will become better at planning realistically. And it is this part of the planning process that you will do last.
The best way to plan the cost of a project is to consider all the factors involved and how those factors relate to time and standard of delivery. Write these down on a spreadsheet format and begin the task of costing and estimating. The company that you’re employed by will always have their own systems in place for doing this. They will also indicate the kind of profit they are looking for-usually in percentage terms.
The second stage of planning is the allocation of time to a project and for this, you’ll have to canvass others for help. Only by asking the advice and opinions of those with expertise in the field, will you be able to establish the size of each unit of work to be completed and the order in which those units of work should be carried out. Remember that some units of work may be done simultaneously but many cannot. In your tutorials this week, you’ll be introduced to the Gant Chart-that’s G-A-N-T. This method of planning project activities has been very successful in the field of project management. The complete set of tasks involved in a project are identified and then planned in relation to each other. You’ll soon discover that organizing and prioritizing activities is quite an art-form.
The third part of your planning as I said, will affect your money and time considerations and that is the standard of delivery that the project demands. These standards will be outlined in the tender documents if they’ve been your guide or the masterplan from which you’re working. Always make sure that you’ve got ALL of the project-related documents that are available. For every unit of work that is to be completed, you’ll have to write specifications-they are detailed descriptions outlining specific standards of quality in materials and labour. If these specifications are not carefully written and then complied with, the project is unlikely to be successful. These specifications will be referred to many times once the project is underway.
You will also have to deal with a Quality Assurance Manager at this stage who will advise you on the standards which need to be met. Quality management has become a valued component in successful project management companies.
I’ve provided you with an outline of the planning process for project management but you’ll be looking at these three elements in more depth in your tutorials this week.
选项
答案
Gant Chart
解析
转载请注明原文地址:https://kaotiyun.com/show/EDAO777K
本试题收录于:
雅思听力题库雅思(IELTS)分类
0
雅思听力
雅思(IELTS)
相关试题推荐
Jacobfeltgreat______abouthisupcomingtriptoBrazil;indeed,hecouldhardlycontainhisenthusiasm.
Governmentofficialsauthorized______becausetheywanttohaveacompleteenumerationofthecountry’spopulation.
Rebeccaknewthattofinishherprojectshemustovercomehertendencytoward______andlearntomakeuphermind.
Indireneedof______,thetravelersfortifiedthemselveswithfoodanddrinkinordertocompletetheirjourney.
Althoughthepoliticalscienceprofessor’spaperisquite(i)______aboutthegovernment’sproblems,suggestingthattheyarepa
AlthoughsomeskepticspointstoArcticplacessuchasthehighlatitudesofGreenland,wheretemperaturesseemtohavefallen,
Inearly-twentieth-centuryEngland,itwasfashionabletoclaimthatonlyacompletelynewstyleofwritingcouldaddressaworl
Whatarethepurposesofplacessuchasmuseumsandhowshouldtheybefunded?
ReadthetextbelowandanswerQuestions8-14.*Onlyonediscountmayapplytoeachfare.CHANGESANDREFUNDSTicketsmaybere
A、Thelibraryclosesearlierduringthesummer.B、Thelibraryisclosedduringsummervacation.C、Thelibrarywillbeopenuntil
随机试题
下列主要用于指导ARDS机械通气参数设置的呼吸环是
A.黄连解毒汤B.宣毒发表汤C.清咽下痰汤D.清解透表汤E.羚角钩藤汤治疗麻疹初热期应首选的方剂是
患者,女,25岁。刷牙后牙龈出血,血色鲜红,伴齿龈红肿疼痛,口臭,舌红,苔黄,脉洪数。该患者进行辨证论治时,其治法为
期货公司应当在本公司网站和营业场所提示客户可以通过()查询其从业人员资格公示信息。
青少年美术作品是青少年身体发展水平、知觉能力、情感态度和生活经验的产物。下列关于青少年绘画作品的主要特点说法错误的是()。
下列选项中,属于对学习者分析的内容的是()。
心理契约是指个体与组织之间隐含的没有明文规定的双方各自的责任及对对方的期望。根据上述定义,下列属于建立心理契约的措施是:
从所给的四个选项中,选择最合适的一个填入问号处,使之呈现一定的规律性。
为什么说传播的过程可以理解为意义与符号的两度“翻译”过程?(上海大学2002研)
加工一个零件,甲需3分钟,乙需3.5分钟,丙需4分钟,现有1825个零件要加工,为尽早完成任务,甲、乙、丙各加工一定数量零件,那么完成任务所需时间最少是()小时.
最新回复
(
0
)