Project work packages are typically decomposed into smaller components called activities to provide a basis for (72) ,scheduling

admin2010-01-17  39

问题 Project work packages are typically decomposed into smaller components called activities to provide a basis for (72) ,scheduling, executing, and monitoring and controlling the project work.

选项 A、reviewing
B、estimating
C、auditing
D、expecting

答案B

解析 把项目工作包分解成更小的结构称为活动的单元,为估算、进度安排、项目执行、项目监控提供了基础。
转载请注明原文地址:https://kaotiyun.com/show/ZHGZ777K
0

相关试题推荐
最新回复(0)