(72) from one phase are usually reviewed for completeness and accuracy and approved before work starts on the next phase.

admin2010-01-28  49

问题 (72) from one phase are usually reviewed for completeness and accuracy and approved before work starts on the next phase.

选项 A、Deliverables
B、Milestone
C、Work
D、Process

答案A