Estimating activity durations uses information on activity scope of(74),required resource types,estimated resource quantities,an

admin2009-04-07  37

问题 Estimating activity durations uses information on activity scope of(74),required resource types,estimated resource quantities,and resource calendars.

选项 A、milestone
B、baseline
C、quality
D、work

答案D

解析 估算活动历时使用的信息包括:活动的工作范围、所需资源类型、估算的资源数量以及资源日历。
转载请注明原文地址:https://kaotiyun.com/show/h2GZ777K
0

相关试题推荐
随机试题
最新回复(0)