On some projects,especially ones of smaller scope,activity sequencing,activity resource estimating.Activity duration estimating,

admin2010-01-28  43

问题 On some projects,especially ones of smaller scope,activity sequencing,activity resource estimating.Activity duration estimating,and (71) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.

选项 A、project planning
B、time estimating
C、cost estimating
D、schedule development

答案D

解析
转载请注明原文地址:https://kaotiyun.com/show/uSHZ777K
0

相关试题推荐
最新回复(0)