In approximating costs, the estimator considers the possible causes of variation of the cost estimates, including (26).

admin2009-09-20  35

问题 In approximating costs, the estimator considers the possible causes of variation of the cost estimates, including (26).

选项 A、budget
B、plan
C、risk
D、contract

答案C

解析 在估算成本时,估算者会考虑成本估算偏差的潜在原因,包括风险。