During the risk analysis process, it is determined that one identified risk event cannot be avoided, mitigated, or insured. This

admin2010-01-17  47

问题 During the risk analysis process, it is determined that one identified risk event cannot be avoided, mitigated, or insured. This risk event is a critical item that could cause the project to fail if it occurs. The best option for the project manager is to:(73) .

选项 A、Continue to search for an insurance company that would assume the risk
B、Place special emphasis on the risk event to intensely manage that item and all interfacing items
C、Play down the risk and the team will find a means of overcoming any failure
D、Ignore the risk assessment because any assigned value is a point estimate which is never precisely the expected state of nature

答案A

解析 在项目风险分析过程中,可以确定一个已被识别的风险事件是不可能避免、减轻或转移的。该风险事件是项目的一个关键因素,如果它发生了,则可能导致项目失败。对于项目经理而言,最好的选择是不断地寻找保险公司以规避风险。
转载请注明原文地址:https://kaotiyun.com/show/ATGZ777K
0

相关试题推荐
最新回复(0)