The process of(17)schedule activity durations uses information on schedule activity scope of work, required resource types’ esti

admin2009-09-20  42

问题 The process of(17)schedule activity durations uses information on schedule activity scope of work, required resource types’ estimated resource quantities, and resource calendars with resource availabilities.

选项 A、estimating
B、defining
C、planning
D、sequencing

答案A

解析 估算进度活动历时的过程会用到进度活动工作范围、所需资源类型、估计的资源数量,以及建立在资源可用性上的资源日历等信息。
转载请注明原文地址:https://kaotiyun.com/show/ILGZ777K
0

相关试题推荐
最新回复(0)