The project schedule is more than a document that lays out the activities over time to represent the time dimension of the proje

admin2012-03-26  30

问题 The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision making. As such, the schedule is used by the project management team to ______.

选项 A、measure,delay,record,distribute,analyze,anddirect
B、plan,schedule,monitor,control,report,andforecast
C、promote,highlight,monitor,control,forecast,andreport
D、emphasize,visualize,analyze,conceptualize,report,andrecord

答案B

解析 项目进度计划是规定在一段时间内相关活动的多文档,它代表该项目的时间维度,是一种用于决策的管理工具。因此项目管理团队可用它进行准备(plan)、议程(schedule)、监测(monitor)、控制(control)、报告(report)和预测(forecast)。
转载请注明原文地址:https://kaotiyun.com/show/yZHZ777K
0

相关试题推荐
随机试题
最新回复(0)